Question: 1 / 400

Which of the following statements is true about project baselines?

They can be adjusted at any time without consent

They provide a reference point for measuring project performance

Project baselines serve as essential reference points for measuring project performance throughout the life cycle of a project. They are established at the planning phase and represent the original approved version of a project’s scope, cost, and schedule. By using these baselines, project managers can assess how the project is progressing against the initial plan, identify variances, and implement corrective actions when necessary.

Having a reference point allows for a clear understanding of how actual performance compares to what was planned, ensuring that any deviations can be managed effectively. This makes baselines a fundamental tool for performance management rather than a concept limited to the planning phase or something to be discarded after initiation. Continuous monitoring against these baselines enables informed decision-making and promotes accountability, which is crucial for successful project outcomes.

In summary, the significance of baselines lies in their role as a constant reference throughout the project, helping teams to track progress and make necessary adjustments.

Get further explanation with Examzify DeepDiveBeta

They are only useful during the planning phase

They should be discarded once the project has started